KAROON DAM III – EXCAVATION & CONSOLIDATION OF A PART OF WATER TUNNEL, TRANSITIONS, VERTICAL PART OF SHAFTS, PENSTOCKS, ADITS, ETC

مجتمع تجاری مریم
مجتمع تجاری مریم
phoca_thumb_l_1
پایاب کوثر
پایاب کوثر
مجتمع تجاری مریم

DESCRIPTION:


In Karoon Dam III project, two portal intakes for the first stage of the operation and also one portal intake for the development project of the relevant power plant are constructed.

Two intake tunnels, which are connected to four water tunnels through two bifurcations, finally arrive at four shafts, and the water required for the power plant of Karoon Dam III is transferred through these two tunnels.

SPECIFICATIONS:


  •  Total Length of Tunnels: 1,920.- meters
  • Cross-Section Area: 30 to 340.- square meters
  • Volume of Underground Excavation: 110,000.- cubic meters
  • Volume of Open-cut Excavation: 50,000.- cubic meters
  • Installed Bolts: 80,000.- meters
  • Weight of Mesh: 150,000.- kilograms
  • Shotcrete Area: 50,000.- square meters
سایر پروژه ها

No results found.

Leave a Reply

Your email address will not be published. Required fields are marked *

Fill out this field
Fill out this field
Please enter a valid email address.