(Gulf Storm Tunnel Complementary Operations (Balangistan

پایاب کوثر
پایاب کوثر
پایاب کوثر

Project Description

The Gulf Martyrs Tunnel (Balangistan) is on the Ard-Fadagh axis to shorten the route and increase safety and reduce accidents by removing the impassable lane. Operations subject to the treaty include the trenching of inlet and outlet portals of the tunnel, as well as the completion of a 7-kilometer tunnel drilling project along the main axis

Project Specifications


:The specifics of the operation of this Convention are as follows

Outdoor excavation: 70,000 cubic meter  –

- Shutters: 70,000 square meters
- Mail restraint: 3,500 meters long
- Station: 37 tons